City Pavement Program Update

During the 2025 construction season, the City of Goleta rehabilitated more than 5.2 centerline miles of roadway as part of its ongoing Pavement Management Program. The Arterial Pavement Project focused on improving the City’s main roads, with most major work now complete.

Remaining tasks include slurry seal and striping on select roadways:

  • Hollister Avenue: Cathedral Oaks Drive to Elderberry Drive
  • Storke Road: Hollister Avenue to Bollay Drive
  • Hollister Avenue: Camino Real Marketplace to Storke Road

Crews will return to finish these tasks, though no major traffic impacts are expected.

Additional streets are also now on tap for rehab at the following locations with work anticipated to begin in early February 2026:

  • Pacific Oaks Road: Hollister Avenue to Phelps Road
  • Calle Real: Salisbury Avenue to Rochester Way
  • Verdura Avenue: Carlo Drive to Vega Drive

These repairs will extend the project timeline from Winter 2025 into Spring 2026. Tree replanting along Berkeley Road and Stow Canyon is also scheduled to begin in February 2026.

The Residential Resurfacing Project in northeast Goleta completed its first phase in 2025. Phase two, which includes slurry seal treatment, is planned for spring 2026, weather permitting. Residents will receive advance notifications, including mailed notices, before construction begins. Work is expected to continue into early summer 2026.

Finally, the City is underway designing the 2026 Arterial Pavement Project and the 2026 Residential Resurfacing Project.

For the latest updates, visit the project webpage, which will provide confirmed schedules. Please note that timelines may change due to material availability, weather, or equipment issues.

Questions? Contact us:
Email: pavement@cityofgoleta.gov
Phone: 805-562-5504
Website: CityofGoleta.org/pavement


Paving work on Storke Road near Camino Real Marketplace


Paving work on Hollister Avenue by Viajero Drive